Project Description
TRCC assisted with the Site C Clean Energy Project with the development and operation of a new gravel pit, the haul of granular material to locations within the Site C Dam site, the upgrading and maintenance of an existing access road to accommodate year-round traffic, and upgrading to existing rail crossing infrastructure.
Scope of Work
Project Overview
Client: BC Hydro
Site Location: Site C Dam near Fort St. John, BC
Completion Date: 2022-2023
Project Value: $37,000,000
TRCC assisted with the Site C Clean Energy Project with the development and operation of a new gravel pit, the haul of granular material to locations within the Site C Dam site, the upgrading and maintenance of an existing access road to accommodate year-round traffic, and upgrading to existing rail crossing infrastructure.
Scope of Work
- Provided all site facilities such as construction fencing necessary to perform work.
- Survey (Construction layout, payment quantities, as-built survey, and others as required).
- Production of Fill Zone 3 Material and 50 mm Crushed Pit Run.
- Excavated, graded, and embankment upgrade to the Ice Bridge Road, including snow clearing, drainage features, and processing, hauling, and placement of Winter Abrasive.
- Excavated roadside ditches and installed drainage culverts, including backfill and bedding.
- Hauled approximately 1,953,000 tonnes of Fill Zone 3 Material from Area E Gravel Pit and delivered to designated locations in Area A.
- Site cleaned up of the Area E Gravel Pit.
Project Overview
Client: BC Hydro
Site Location: Site C Dam near Fort St. John, BC
Completion Date: 2022-2023
Project Value: $37,000,000