Project Description
Tangle Ridge successfully managed and completed the realignment and reconstruction of a 4.4 km section of the Alaska Highway, from Km 565.9 to Km 570.32, between Fort Nelson, BC and Watson Lake, YT.
Scope of Work
Project Overview
Client: Public Service Procurement Canada
Site Location: Tetsa River, BC
Completion Date: 2022
Project Value: $5,100,000
Tangle Ridge successfully managed and completed the realignment and reconstruction of a 4.4 km section of the Alaska Highway, from Km 565.9 to Km 570.32, between Fort Nelson, BC and Watson Lake, YT.
Scope of Work
- Removed stumps and stripped organic materials within the designated construction footprint, including loading, hauling and offsite disposal.
- Excavated, transported, placed, and compacted approximately 100,000 m³ of material for roadway embankment.
- Compacted and combined approximately 50,000 m³ of crushed base gravel, sub-base course, and select subgrade fill material for roadway construction.
- Supplied and installed drainage infrastructure at 15 locations, including corrugated steel pipe (CSP) culverts, fish baffles, bentonite, natural substrate, culvert inlet and outlet riprap protection, inlet and outlet realignment, and ditch construction.
- Completed final site grading and landscape restoration.
Project Overview
Client: Public Service Procurement Canada
Site Location: Tetsa River, BC
Completion Date: 2022
Project Value: $5,100,000