Project Description
Tangle Ridge executed the remediation of a petroleum hydrocarbon soils at a former highway maintenance yard in Trutch, British Columbia. The overall project goals were to remove Petroleum Hydrocarbon impacted soils to ensure the environmental liabilities were properly managed and or removed. Work was successfully completed in a remote location during extreme winter weather conditions.
Scope of Work
Project Overview
Client: Public Service Procurement Canada
Site Location: Trutch, BC
Completion Date: 2020
Project Value: $2,250,000
Tangle Ridge executed the remediation of a petroleum hydrocarbon soils at a former highway maintenance yard in Trutch, British Columbia. The overall project goals were to remove Petroleum Hydrocarbon impacted soils to ensure the environmental liabilities were properly managed and or removed. Work was successfully completed in a remote location during extreme winter weather conditions.
Scope of Work
- Provided all site facilities such as heated office and living quarters, and suitable excavation equipment necessary to perform the work.
- Developed and implemented a comprehensive Safety Plan to safely execute the work.
- Completed the initial and final site topographic surveys.
- Excavated, loaded, transported, and disposed of approximately 20,000 metric tonnes of impacted soil to landfill.
- Loaded, transported, and placed 13,250 m³ of backfill sourced from Highways Department gravel pit.
- Completed final site grading and landscape restoration.
Project Overview
Client: Public Service Procurement Canada
Site Location: Trutch, BC
Completion Date: 2020
Project Value: $2,250,000